Plans to build an accessible splash pad at Cantine Field Complex in Saugerties have been delayed by engineering studies required for a state grant, Deputy Town Supervisor Leeanne Thornton said.

The town had hoped to begin construction before winter. Officials now aim to finish planning over the winter to take advantage of the spring construction season, Supervisor Fred Costello said. Thornton hopes to have the splash pad open next summer.

“We were hoping we could get shovels in the ground before we have a heavy frost or deep freeze this winter,” Thornton said.

The additional review is needed because the planned site, off Washington Avenue and Bob Moser Drive, is low-lying, Thornton said. Town engineer Dennis Larios will determine what work is needed to prepare the ground for construction.

The splash pad, a flat play area with water sprays, is planned next to the complex’s kiddie pool. It will be designed to accommodate people with disabilities and will be free and open to the public during the summer.

The Community Foundation of Saugerties began raising money for the project in 2025, with an initial goal of $400,000. The foundation had raised more than $80,000 by July. Costs have since risen, Thornton said.

The foundation received a $605,000 grant in June from the New York State Office of Parks, Recreation and Historic Preservation after two unsuccessful applications, Thornton said. The engineering studies are required to meet the grant’s conditions.

In July, organizers said proceeds from a food truck fundraiser would help pay for a wheelchair-accessible path to the splash pad and other parks and recreation needs.

Organizers are considering two vendors. Parkitects, based in Buffalo, quoted a total cost of $627,463, Thornton said. Vortex is also under consideration and has yet to submit a design or quote.

Thornton expects final designs by Dec. 1 and hopes some preliminary groundwork can be completed before Jan. 1. Construction is expected to take at least three to four months once it begins, she said.

Isabella Schoonover is a staff reporter for The Overlook covering Woodstock, Saugerties, Hurley, and surrounding Ulster County communities. Send correspondence to isabella@theoverlooknews.com.


"*" indicates required fields

This field is for validation purposes and should be left unchanged.
Have a tip for a story or an issue in your community? See something happening we should know about? Let us know!

Isabella Schoonover completed her master's degree at the Medill School of Journalism at Northwestern University. There, she specialized in solutions and community-based journalism, investigated multinational...